[Federal Register Volume 85, Number 164 (Monday, August 24, 2020)]
[Notices]
[Pages 52114-52115]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-18509]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP20-507-000]


Transcontinental Gas Pipe Line Company, LLC; Sea Robin Pipeline 
Company, LLC; Florida Gas Transmission Company, LLC; Notice of 
Application

    Take notice that on August 6, 2020, Transcontinental Gas Pipe Line 
Company, LLC (Transco), P.O. Box 1396, Houston, Texas 77251, Sea Robin 
Pipeline Company, LLC (Sea Robin), 1300 Main Street. Houston, Texas 
77002, and Florida Gas Transmission Company, LLC (FGT), 1300 Main 
Street. Houston, Texas 77002, jointly filed an application in the above 
referenced docket pursuant to section 7(b) of the Natural Gas Act (NGA) 
and part 157 of the Commission's regulations requesting authorization 
to abandon approximately 12.6 miles of 24-inch-diameter lateral 
pipeline extending from offshore Vermilion Parish, Louisiana, at the 
Vermilion Area Block 22 subsea tie-in to a point of connection with 
Transco's Central Louisiana Gathering System onshore in the Pecan 
Island area, Vermilion Parish, Louisiana, and related metering 
facilities, all as more fully set forth in the application which is on 
file with the Commission and open to public inspection.
    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (http://ferc.gov) using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. At this time, 
the Commission has suspended access to the Commission's Public 
Reference Room, due to the proclamation declaring a National Emergency 
concerning the Novel Coronavirus Disease (COVID-19), issued by the 
President on March 13, 2020. For assistance, contact FERC at 
FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TYY, 
(202) 502-8659.
    Any questions concerning this application may be directed to Nick 
Baumann, Regulatory Analyst, Transcontinental Gas Pipe Line Company, 
P.O. Box 1396, Houston, Texas 77251, (281) 714-7056; Deborah A. 
Bradbury, Sr. Director, Regulatory Tariffs & Reporting, Sea Robin 
Pipeline Company, 1300 Main Street, Houston, Texas 77002, (713) 989-
7571; or Blair Lichtenwalter, Senior Director, Certificates, Florida 
Gas Transmission Company, 1300 Main Street, Houston, Texas 77002, (713) 
989-2605.
    Pursuant to section 157.9 of the Commission's rules (18 CFR 157.9), 
within 90 days of this Notice, the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule will serve to 
notify federal and state agencies of the timing for the completion of 
all necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit five copies of filings made with the Commission and must mail a 
copy to the applicant and to every other party in the proceeding. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list and will be 
notified of meetings associated with the Commission's environmental 
review process. Environmental commenters will not be required to serve 
copies of filed documents on all other parties. However, the non-party 
commenters will not receive copies of all documents filed by other 
parties or issued by the Commission and will not have the right to seek 
court review of the Commission's final order.
    As of the February 27, 2018 date of the Commission's order in 
Docket No. CP16-4-001, the Commission will apply its revised practice 
concerning out-of-time motions to intervene in any new NGA section 3 or 
section 7 proceeding.\1\ Persons desiring to become a party to a 
certificate proceeding are to intervene in a timely manner. If seeking 
to intervene out-of-time, the movant is required to ``show good cause 
why the time limitation should be waived,'' and should provide 
justification by reference to factors set forth in Rule 214(d)(1) of 
the Commission's Rules and Regulations.\2\
---------------------------------------------------------------------------

    \1\ Tennessee Gas Pipeline Company, L.L.C., 162 FERC ] 61,167 at 
] 50 (2018).
    \2\ 18 CFR 385.214(d)(1).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFile'' link at 
http://www.ferc.gov.

[[Page 52115]]

In lieu of electronic filing, you may submit a paper copy. Submissions 
sent via the U.S. Postal Service must be addressed to: Kimberly D. 
Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street 
NE, Room 1A, Washington, DC 20426. Submissions sent via any other 
carrier must be addressed to: Kimberly D. Bose, Secretary, Federal 
Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 
20852.
    Comment Date: 5:00 p.m. Eastern Time on September 7, 2020.

    Dated: August 17, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020-18509 Filed 8-21-20; 8:45 am]
BILLING CODE 6717-01-P