[Federal Register Volume 85, Number 165 (Tuesday, August 25, 2020)]
[Notices]
[Page 52338]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-18582]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

 [Docket No. CP17-458-000]


Midship Pipeline Company, LLC; Notice of Request for Extension of 
Time

    Take notice that on August 10, 2020, Midship Pipeline Company, LLC 
(Midship) requested that the Federal Energy Regulatory Commission 
(Commission) grant an extension of time, until December 31, 2022, to 
complete construction and place into service three delayed compressor 
units for its Midship Pipeline Project, as originally authorized in the 
August 13, 2018 Order Issuing Certificate (August 13 Order).\1\ The 
August 13 Order (as amended) \2\ required the applicants to complete 
construction and make the facilities available for service within two 
years of the original Order date.
---------------------------------------------------------------------------

    \1\ Midship Pipeline Company, LLC, 164 FERC ] 61,103 (2018).
    \2\ Midship Pipeline Company, LLC, 166 FERC ] 62,039 (2019); 
Midship Pipeline Company, LLC, 168 FERC ] 61,147 (2019); Midship 
Pipeline Company, LLC, 170 FERC ] 61,137 (2020).
---------------------------------------------------------------------------

    The overall project is designed to provide up to 1,440 million 
standard cubic feet per day (MMcf/d) of firm transportation capacity 
from the South Central Oklahoma Oil Province and the Sooner Trend 
Anadarko Basin Canadian and Kingfisher gas plays in the Anadarko Basin 
in Oklahoma to existing natural gas pipelines near Bennington, 
Oklahoma, for subsequent transport to Gulf Coast and Southeast markets. 
As authorized, the project includes an approximately 200-mile-long 
mainline pipeline in Oklahoma; three mainline gas-fired turbine 
compressor stations (Calumet, Tatums and Bennington), each of which 
included three compressor units; metering and regulation stations; 
appurtenant facilities; and two lateral pipelines, the Chisholm and 
Velma Laterals.
    In its request, Midship states that it has constructed all 
facilities authorized by the Certificate, except for one compressor 
unit at each of the Calumet, Tatums, and Bennington compressor 
stations.
    Midship also states that, due to delays in the commercialization of 
the project, additional time is now required in order to complete the 
construction of the remaining authorized project facilities.
    This notice establishes a 15-calendar day intervention and comment 
period deadline. Any person wishing to comment on the applicant's 
request for an extension of time may do so. No reply comments or 
answers will be considered. If you wish to obtain legal status by 
becoming a party to the proceedings for this request, you should, on or 
before the comment date stated below, file a motion to intervene in 
accordance with the requirements of the Commission's Rules of Practice 
and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the 
Natural Gas Act (18 CFR 157.10).\3\
---------------------------------------------------------------------------

    \3\ Only motions to intervene from entities that were party to 
the underlying proceeding will be accepted. Algonquin Gas 
Transmission, LLC, 170 FERC ] 61,144, at P 39 (2020).
---------------------------------------------------------------------------

    As a matter of practice, the Commission itself generally acts on 
requests for extensions of time to complete construction for Natural 
Gas Act facilities when such requests are contested before order 
issuance. For those extension requests that are contested,\4\ the 
Commission will aim to issue an order acting on the request within 45 
days.\5\ The Commission will address all arguments relating to whether 
the applicant has demonstrated there is good cause to grant the 
extension.\6\ The Commission will not consider arguments that re-
litigate the issuance of the certificate order, including whether the 
Commission properly found the project to be in the public convenience 
and necessity and whether the Commission's environmental analysis for 
the certificate complied with the National Environmental Policy Act.\7\ 
At the time a pipeline requests an extension of time, orders on 
certificates of public convenience and necessity are final and the 
Commission will not re-litigate their issuance.\8\ The OEP Director, or 
his or her designee, will act on all of those extension requests that 
are uncontested.
---------------------------------------------------------------------------

    \4\ Contested proceedings are those where an intervenor disputes 
any material issue of the filing. 18 CFR 385.2201(c)(1) (2019).
    \5\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40 
(2020).
    \6\ Id. at P 40.
    \7\ Similarly, the Commission will not re-litigate the issuance 
of an NGA section 3 authorization, including whether a proposed 
project is not inconsistent with the public interest and whether the 
Commission's environmental analysis for the permit order complied 
with NEPA.
    \8\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40 
(2020).
---------------------------------------------------------------------------

    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (http://www.ferc.gov) using 
the ``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. At this time, 
the Commission has suspended access to Commission's Public Reference 
Room, due to the proclamation declaring a National Emergency concerning 
the Novel Coronavirus Disease (COVID-19), issued by the President on 
March 13, 2020. For assistance, contact FERC at 
FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TYY, 
(202) 502-8659.
    The Commission strongly encourages electronic filings of comments 
in lieu of paper using the ``eFile'' link at http://www.ferc.gov. In 
lieu of electronic filing, you may submit a paper copy. Submissions 
sent via the U.S. Postal Service must be addressed to: Kimberly D. 
Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street 
NE, Room 1A, Washington, DC 20426. Submissions sent via any other 
carrier must be addressed to: Kimberly D. Bose, Secretary, Federal 
Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 
20852.
    Comment Date: 5:00 p.m. Eastern Time on September 1, 2020.

    Dated: August 17, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-18582 Filed 8-24-20; 8:45 am]
BILLING CODE 6717-01-P