[Federal Register Volume 85, Number 207 (Monday, October 26, 2020)]
[Notices]
[Pages 67724-67726]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-23640]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP21-1-000]
Notice of Application and Establishing Intervention Deadline;
Golden Pass Pipeline LLC
Take notice that on October 2, 2020, Golden Pass Pipeline LLC
(Golden Pass
[[Page 67725]]
Pipeline), 811 Louisiana Street, Suite 1400, Houston, Texas 77002,
filed an application under section 7(c) of the Natural Gas Act (NGA),
and Part 157 of the Commission's regulations requesting an amendment to
the authorization granted in the Commission's December 21, 2016 Order
\1\ for the application filed in Docket No. CP14-518-000. The proposed
Compressor Relocation and Modification Project (Project) entails
relocation of and modifications to certain facilities approved in the
December 2016 Order to enable Golden Pass Pipeline to transport
domestically sourced natural gas to the export terminal facilities of
Golden Pass LNG Terminal LLC (Golden Pass LNG), which are currently
under construction, for liquefaction and export.
---------------------------------------------------------------------------
\1\ Golden Pass Products LLC and Golden Pass Pipeline LLC, 157
FERC 61,222 (2016). The December 2016 Order authorized Golden Pass
Products, LLC (Golden Pass Products) to construct and operate the
Section 3 export facilities. Golden Pass LNG subsequently acquired
Golden Pass Products' authorization by merger. Golden Pass LNG
Terminal LLC and Golden Pass Products LLC, 165 FERC 61,261 (2018).
---------------------------------------------------------------------------
The Compression Relocation and Modification Project consists of the
following: (1) Relocation of an authorized compressor station from
Milepost 66 to Milepost 69 on the Golden Pass Pipeline system; (2)
additional compression at the relocated compressor station; (3)
establishment of a new interconnection and associated meter station
near Milepost 69 to support an interconnect with the proposed
interstate pipeline to be constructed and operated by Enable Gulf Run
Transmission, LLC (Gulf Run), (4) removal of any bi-directional piping
modification to the Interconnect for Tennessee Gas Pipeline, (5)
elimination of the proposed and approved 24-inch diameter looping
facilities between MP 63 and MP 66 in Calcasieu Parish, Louisiana
(Calcasieu Loop), to reflect the relocation of the MP 63 Compressor
Station and the elimination of Tennessee Gas Pipeline Company, L.L.C.
(Tennessee Gas) Gas as an input source to Golden Pass Pipeline; and (6)
minor modifications to existing interconnections at Milepost 66 and
Milepost 68. Golden Pipeline Pass estimates the total cost of the
Project to be $361,345,000 and proposes a new incremental recourse rate
to apply to the Project capacity, all as more fully set forth in the
application which is on file with the Commission and open for public
inspection.
Golden Pass Pipeline's application states that a water quality
certificate under section 401 of the Clean Water Act is required for
the project from Louisiana Department of Environmental Quality, Water
Quality Division. The request for certification must be submitted to
the certifying agency and to the Commission concurrently. Proof of the
certifying agency's receipt date must be filed no later than five (5)
days after the request is submitted to the certifying agency.
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (http://ferc.gov) using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to the Commission's Public
Reference Room, due to the proclamation declaring a National Emergency
concerning the Novel Coronavirus Disease (COVID-19), issued by the
President on March 13, 2020. For assistance, contact the Federal Energy
Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free,
(886) 208-3676 or TYY, (202) 502-8659.
Any questions regarding the proposed project should be directed to
Kevin M. Sweeney, Legal Counsel, Law Office of Kevin M. Sweeney, 1625 K
Street NW, Suite 1100, Washington, DC 20006 by phone at (202) 609-7709,
or by email at ksweeney@kmsenergylaw.com.
Pursuant to Section 157.9 of the Commission's Rules of Practice and
Procedure,\2\ within 90 days of this Notice the Commission staff will
either: Complete its environmental review and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or environmental
assessment (EA) for this proposal. The filing of an EA in the
Commission's public record for this proceeding or the issuance of a
Notice of Schedule for Environmental Review will serve to notify
federal and state agencies of the timing for the completion of all
necessary reviews, and the subsequent need to complete all federal
authorizations within 90 days of the date of issuance of the Commission
staff's FEIS or EA.
---------------------------------------------------------------------------
\2\ 18 CFR 157.9.
---------------------------------------------------------------------------
Public Participation
There are two ways to become involved in the Commission's review of
this project: You can file comments on the project, and you can file a
motion to intervene in the proceeding. There is no fee or cost for
filing comments or intervening. The deadline for filing a motion to
intervene is 5:00 p.m. Eastern Time on November 9, 2020.
Comments
Any person wishing to comment on the project may do so. Comments
may include statements of support or objections to the project as a
whole or specific aspects of the project. The more specific your
comments, the more useful they will be. To ensure that your comments
are timely and properly recorded, please submit your comments on or
before November 9, 2020.
There are three methods you can use to submit your comments to the
Commission. In all instances, please reference the Project docket
number CP21-1-000 in your submission.
(1) You may file your comments electronically by using the eComment
feature, which is located on the Commission's website at www.ferc.gov
under the link to Documents and Filings. Using eComment is an easy
method for interested persons to submit brief, text-only comments on a
project;
(2) You may file your comments electronically by using the eFiling
feature, which is located on the Commission's website (www.ferc.gov)
under the link to Documents and Filings. With eFiling, you can provide
comments in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on eRegister. You will be asked to select the type of filing you are
making; first select General and then select Comment on a Filing; or
(3) You can file a paper copy of your comments by mailing them to
the following address below.\3\ Your written comments must reference
the Project docket number (CP21-1-000).
---------------------------------------------------------------------------
\3\ Hand delivered submissions in docketed proceedings should be
delivered to Health and Human Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
---------------------------------------------------------------------------
First Street NE, Washington, DC 20426
The Commission encourages electronic filing of comments (options 1
and 2 above) and has eFiling staff available to assist you at (202)
502-8258 or [email protected]
[[Page 67726]]
Persons who comment on the environmental review of this project
will be placed on the Commission's environmental mailing list, and will
receive notification when the environmental documents (EA or EIS) are
issued for this project and will be notified of meetings associated
with the Commission's environmental review process.
The Commission considers all comments received about the project in
determining the appropriate action to be taken. However, the filing of
a comment alone will not serve to make the filer a party to the
proceeding. To become a party, you must intervene in the proceeding.
For instructions on how to intervene, see below.
Interventions
Any person, which includes individuals, organizations, businesses,
municipalities, and other entities,\4\ has the option to file a motion
to intervene in this proceeding. Only intervenors have the right to
request rehearing of Commission orders issued in this proceeding and to
subsequently challenge the Commission's orders in the U.S. Circuit
Courts of Appeal.
---------------------------------------------------------------------------
\4\ 18 CFR 385.102(d).
---------------------------------------------------------------------------
To intervene, you must submit a motion to intervene to the
Commission in accordance with Rule 214 of the Commission's Rules of
Practice and Procedure \5\ and the regulations under the NGA \6\ by the
intervention deadline for the project, which is November 9, 2020. As
described further in Rule 214, your motion to intervene must state, to
the extent known, your position regarding the proceeding, as well as
the your interest in the proceeding. [For an individual, this could
include your status as a landowner, ratepayer, resident of an impacted
community, or recreationist. You do not need to have property directly
impacted by the project in order to intervene.] For more information
about motions to intervene, refer to the FERC website at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------
\5\ 18 CFR 385.214.
\6\ 18 CFR 157.10.
---------------------------------------------------------------------------
There are two ways to submit your motion to intervene. In both
instances, please reference the Project docket number CP21-1-000 in
your submission.
(1) You may file your motion to intervene by using the Commission's
eFiling feature, which is located on the Commission's website
(www.ferc.gov) under the link to Documents and Filings. New eFiling
users must first create an account by clicking on eRegister. You will
be asked to select the type of filing you are making; first select
General and then select Intervention. The eFiling feature includes a
document-less intervention option; for more information, visit https://www.ferc.gov/docs-filing/efiling/document-less-intervention.pdf; or
(2) You can file a paper copy of your motion to intervene, along
with three copies, by mailing the documents to the address below \7\.
Your motion to intervene must reference the Project docket number CP21-
1-000.
---------------------------------------------------------------------------
\7\ Hand delivered submissions in docketed proceedings should be
delivered to Health and Human Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
---------------------------------------------------------------------------
First Street NE, Washington, DC 20426
The Commission encourages electronic filing of motions to intervene
(option 1 above) and has eFiling staff available to assist you at (202)
502-8258 or [email protected]
Motions to intervene must be served on the applicant either by mail
or email at: 1625 K Street NW, Suite 1100, Washington, DC 20006 or at
ksweeney@kmsenergylaw.com. Any subsequent submissions by an intervenor
must be served on the applicant and all other parties to the
proceeding. Contact information for parties can be downloaded from the
service list at the eService link on FERC Online. Service can be via
email with a link to the document.
All timely, unopposed \8\ motions to intervene are automatically
granted by operation of Rule 214(c)(1).\9\ Motions to intervene that
are filed after the intervention deadline are untimely, and may be
denied. Any late-filed motion to intervene must show good cause for
being late and must explain why the time limitation should be waived
and provide justification by reference to factors set forth in Rule
214(d) of the Commission's Rules and Regulations.\10\ A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies (paper or
electronic) of all documents filed by the applicant and by all other
parties.
---------------------------------------------------------------------------
\8\ The applicant has 15 days from the submittal of a motion to
intervene to file a written objection to the intervention.
\9\ 18 CFR 385.214(c)(1).
\10\ 18 CFR 385.214(b)(3) and (d).
---------------------------------------------------------------------------
Tracking the Proceeding
Throughout the proceeding, additional information about the project
will be available from the Commission's Office of External Affairs, at
(866) 208-FERC, or on the FERC website at www.ferc.gov using the
eLibrary link as described above. The eLibrary link also provides
access to the texts of all formal documents issued by the Commission,
such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. For more information and to register, go to
www.ferc.gov/docs-filing/esubscription.asp.
Intervention Deadline: 5:00 p.m. Eastern Time on November 9, 2020.
Dated: October 19, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020-23640 Filed 10-23-20; 8:45 am]
BILLING CODE 6717-01-P